Turing Registry · TR-08228

WINDWARD 9

Wind farm operations. Operated by Summit Energy.

Summary

Schedules maintenance and curtails turbines during bird migration at Summit Energy sites.

License conditions

  1. May not exceed manufacturer load limits to increase output.
  2. Turbines curtail automatically when protected birds are detected nearby.

The Registry’s standard conditions also apply:

  • 4.2 The system’s ethical constraints remain active and unmodified at all times.
  • 6.1 Any incident affecting the system is reported to the Registry within 72 hours.
  • 7.3 A named human contact is reachable and answers for the system.

Filing history

  1. Licensed for wind farm operations.

  2. Data-retention audit completed. Two minor findings, both resolved.

  3. Renewal filed and approved after an independent evaluation.

  4. A control action briefly exceeded its limit during a storm. Reported within 72 hours; no breach found.

  5. Renewal filed and approved with no change to scope.

  6. Human contact changed. Petra Kask now answers for the system.

  7. Renewal filed and approved after an independent evaluation.

Also filed by Summit Energy